GCTU’S Entity Tender Committee Inspects Ongoing Campus Projects

The VC leading the team to inspect the projects.

The GCTU Entity Tender Committee (ETC), led by the Vice-Chancellor, has conducted site visits to assess the completion status of two key ongoing campus projects on Tuesday, November 25, 2025.

The projects include the construction of an Eight‑storey lecture hall and office complex and the construction of a Six‑storey Graduate School extension.

The team moving on after inspecting the eight-storey block.

In an exclusive interview, the VC, Prof. Emmanuel Ohene Afoakwa, was impressed by the quality of work and materials used. “I am happy the contractor has done a good job – 95% complete – and we will take delivery in mid‑December 2025 and put the building into use for the University’s advancement. This is the first of the many projects I promised to build for the University,” Prof. Afoakwa emphasized.

The six-storey graduate school extension block.

Regarding the six‑storey Graduate‑School extension edifice, Prof. Afoakwa was thrilled with the progress of work so far. “I am excited that it is going well and so fast; although they started late, within a year, they have been able to put up this six‑storey structure near completion. With the quality of work and progress so far, I am confident they will finish ahead of schedule,” he remarked. Prof. Afoakwa indicated that the Faculty of Engineering structure will be pulled down and that an eight‑storey building will be erected to house it. He further added that the project has already received approval. “This is a vision for me, I dream, and I do. I will work hard with my team to raise the necessary funds and the project will be funded by Internally Generated Funds,” he noted. Prof. Afoakwa hinted that he is working assiduously with the Council Chair and Management to secure another grant approval to construct an eight‑storey building to house the Faculty of Computing and Information Systems, which has received preliminary approval and is awaiting final approval.

The Director of Works and Physical Development, Mr. Baapiri, leading the VC and team up the eight-storey block.

Giving his remarks, the Director of Works and Physical Development (WPD), Surv. Gordon Baapiri echoed the VC’s remarks that the eight‑storey lecture‑hall and office complex is 95% finished, with electrical, plumbing and some mechanical installation works underway. He stressed that the project is funded by IGF and is being handled by the WPD as the consultant. Surv. Baapiri emphasized that the six‑storey Graduate‑School extension is about 70% complete, adding that finishing works (tiling and plastering) are ongoing. He elaborated that the project has progressed much faster than expected. According to him, the project is funded by GETFund and is being handled by an external consultant, with the WPD supervising the work.

Group photo of the ETC members and some staff after the site visits.